27 March, 2024

Drafting of construction projects for eleven sections of the Ebro Resilience Strategy.

The Ebro Resilience Strategy launches the bidding process for four consulting contracts for the drafting of the construction projects of sections 3A, 3B, 4, 5, 6, 8, 10, 11, 12B, 15 and 16. The Ebro Resilience Strategy is developing a […]
22 March, 2024
Estrategia Ebro Resilience y Proyecto LIFE Ebro Resilience P1

Ebro Resilience Strategy and LIFE Ebro Resilience Project P1

Coordination and participation as a tool to achieve a more flood-resilient middle Ebro, improving the ecological status and local biodiversity. In the framework of World Water Day, which is celebrated every March 22nd, the Strategy Ebro Strategy Resilience Strategy Strategy […]
21 March, 2024
Vista del meandro y del cauce de alivio de La Roza, Alfaro, La Rioja

The relief channel in the meander of La Roza: a riparian corridor with more continuity and diversity for habitats.

The restoration of vegetation that is being carried out with vegetation typical of the Ebro riverbank in this channel, created during the morphological adaptation, gives us the excuse to talk about this type of intervention.
13 March, 2024
Meandro de la roza con máximos caudales registrados en el episodio de crecidas (unos 2.000 m3/s) en el tramo medio.

Ebro Resilience Interventions: a review in images of the last flooding of the river

The last week of February has seen a flood of flows in the middle stretch of the Ebro due to the rains recorded in the Ebro basin, an episode at the limit of what is considered extraordinary that leaves us these images of the response of the Ebro Resilience intervention typologies in this stretch
29 February, 2024

Ideas and proposals from the territory: LIFE Ebro Resilience P1 opens new avenues of participation on the use of land in El Señorío

The Project organizes an open forum on future uses in this meander that will recover its function as a natural space, a public activity that was also carried out to gather proposals in the meander of La Roza, in Alfaro.
20 February, 2024
Trabajos de instalación de la tubería de hormigón para el sistema de riegos de la Comunidad Huerta del Ebro, en Fuentes de Ebro (Zaragoza)

Installing the new pipeline that adapts the irrigation system in Fuentes de Ebro to the risk of flooding.

The laying of the new concrete pipe, with a total length of 2,300 meters in this phase, which moves this infrastructure away from the riverbed in the Huerta del Ebro Irrigation Community, is in progress.
9 February, 2024
Plantación realizada durante la restauración ambeintal

La Roza environmental restoration underway, last step to complete the LIFE intervention in this meander

- These works are being carried out by the Government of La Rioja and will involve the planting of more than 4,600 specimens of riparian species imitating the natural growth of riparian vegetation.
2 February, 2024
Imagen del nuevo humedal creado en el meandro de La Roza, Alfaro, La Rioja

Wetlands in the Ebro Resilience territory: La Nava and La Roza, Alfaro (la Rioja)

In 2023, the meando de La Roza has inaugurated a new wetland area integrated in the morphological adaptation carried out through the LIFE Ebro Resilience P1 Project, in addition to the one created in 2020 in La Nava as part of the actions of the Ebro Resilience Strategy.
30 January, 2024
Obras de adaptación ante inundaciones del sistema de riego de la Comunidad de la Huerta del Ebro en Fuentes de Ebro. realizando la zanja para enterrar la tubería

Provisional irrigation systems enabled during the work to adapt the Ebro Orchard Community system to floods

The scarcity of winter rains has allowed progress to be made on the work, but unfortunately it is detrimental to crops. For this reason, temporary irrigation has been set up in the fields surrounding the works to save crops, in agreement with the irrigation community and in keeping with the Project's spirit of participation and cooperation.